Friday, July 17, 2009

Albany Project: Fifth Day

The clutter remains -- ladders, scaffolding, cut and un-cut drywall, corner bead, two-by-fours, scraps of this and that, but not nearly as much joint compound as a while ago.

Our finishing work continues. The proscenium arch in the theater has come a long, long way. Now, sheathed in a skim-coat of joint compound, it is almost ready to paint, as are the surrounding walls. Almost, almost.

Further behind is the Oasis. Though every joint now has a coat of mud, much sanding and reapplications remain. The soffits are almost done, too.

With John joining the work crew today, the Theater now has its new door. The closet door is not far behind. Seth has been given a design commission by John to sketch out the marquee. So that, too, may soon be underway.

The projection: two more days of mudding and everything should be ready for a first coat of paint.

Thursday, July 16, 2009

Albany Project: Day Four

Sydney and her father, Jim, joined us today. We also had church members: Susan and Mike, Linda, Ray and Pastor Glenn. NYS-FITS+ included Roland, JoEllen and Tom and Debbie and Eric, with Rose Ann preparing supper.

Our efforts today included a variety of finishing jobs. In the stage area we added more mud, corner bead and underneath trim to the arch. Soon now everything will be ready for the first coat of paint.

Linda was busy painting in the Arts and Crafts area. With just a little more work the Theater will be ready, too.

In the Oasis the mudding continued after the smoke and fire detector was installed and the last piece of drywall lifted into place. Corner bead and mud were added to the soffits. Another coat or two on the ceiling and soffits and everything will be paint-ready.

Wednesday, July 15, 2009

Albany Project: Day Three


Well, today we were supposed to finish, but we didn't make it. Much ground has been covered -- many walls drywalled including the Oasis pyramid, the risers and sink are in place, and the taping and mudding begun -- and yet there is much remaining to be completed.

A reduced crew, less than half the number we had to start, will work the next two days. Perhaps by the end of the week the mudding will be close to being finished. This will include installation of the corner beads and trim around the arch above the stage.

Once again today we were fed a delicious lunch by the Deacons of the church. They have done this all three days and will continue through Friday. Our evening meals are prepared by Joanne, Marcia and Rose Ann. All this good food has helped to keep us going. We truly appreciate all that everyone has done to support our efforts!

Several church members, Marilyn and Phillip, Leslie, Mike, Douglas, and Ray, have worked with us, increasing our output. Miriam and Glenn Leupold, the pastoral team serving the church, have occasionally been able to join us for lunch or dinner. Miriam has also gone the second mile of greeting us each morning with fresh coffee, as we gather in the parking lot.

Tuesday, July 14, 2009

Albany Project: Day Two


After a second long, productive day, the end -- while still distant -- is almost in sight!

The Jericho Theater risers are finished, as is the drywalling in that room -- next comes the taping and mudding. Unknown for the time being is how the rug will be re-attached on the surface. Ron and Jim moved on to drywall the hall closet and finished hanging that by day's end. The door jambs to both the closet and Jericho Theater need re-framing before the doors can be re-hung to complete these areas.

In the Oasis, three of the four walls are drywalled and the insulation is all in place. Two of the corners are done, but these places have been slow-going, as has the pyramid ceiling. This ceiling is over half done but the taping and mudding remain here, too.

The plumbing is finished in the Arts and Crafts area and the sink is in place. The counter and storage area have yet to be completed.

At Sinai Stage, almost all of the drywall work has been finished and all of the large stage extensions are assembled -- two other, triangular pieces remain.

Monday, July 13, 2009

Albany Project: Day One

Eight AM, 18 people gather for introductions, a welcome from Pastor Miriam, stretching and other preliminaries. Tools were then carried to the third floor -- lots of hands, light work! And after architect-designer, John Myers, walked us through the rooms, we divided into four teams and went to work.

Fruits of our labors. By day's end, the Sinai Stage has 8 of its 10 "stage extension platforms" cut and partly assembled and about 2/3 of the needed drywall cut and screwed in place with insulation added to the interior walls. Peg and JoEllen led this crew of 5, Leslie, Mike and Betty assisted.

Kevin and "Papa" Don worked on the plumbing for the Arts & Crafts room. While it took a while to find the requisite drain line and sources of water, if the sink had been on site, they would have been almost ready to begin making connections when work ended.

In Jericho Theater, Ron and Tom led their team of 5, with Jim, Phillip and Ray rounding out their crew. Here, following John's plans, they rolled back the rug and began laying down the riser supports which will soon hold 25 theater seats, once the platforms are installed. By day's end they were ready to begin screwing down the platforms. Besides this, they did some drywalling.

Finally, in the Oasis, or open meeting area, Terry, Peter and Eric worked with Linda, Marilyn and Debbie to install drywall on the walls and ceilings. Work here was slowed because of the ceiling height and tricky hallway corners. When completed this area will also showcase a marquee over the entrance to Jericho Theater. At day's end, more than half the drywall was in place.