Tuesday, March 30, 2010

Friday, March 26th


For all of this week our 19 were supplemented by several from the conference center staff: Gale and Margaret, the caretakers; Janet, the director; and Jean, an intern.

On this day further work in the Center itself, removing and replacing the sliding glass door at the handicapped entrance, and making repairs to the exterior siding and gutters, was completed Three days. Edd, Seth and Keith did this.

Repairs were also made on the residence ceiling to restore the sheetrock that had fallen when it became water-soaked. With ladders and boards stretched across the stair opening, Dave W., Roland, Tom, Eric and Ron somehow all found space to work in this narrow area.