By Wednesday we have begun to hit our stride. Three home sites are being worked on, but our focus is really on just two of them. We hope to complete the rebuilding on at least one of the two.
At Royden and Lina's various floor and baseboard issues have been resolved, the threshold has been corrected, the sink has been centered, the cabinet installed above the stove, molding around the side door has been installed, the hallway and boy's bedroom flooring is almost complete. Seth seems well pleased with his crew!
At Yolanda's, interior window framing has continued, issues with the air conditioning system have been thought through, master bathroom has been sanded, drywall around the tub finished, taping and mudding underway, a door jam expanded to prepare for the baseboard molding, and the baseboard molding was continued. As you might have guessed, Ron is elated!
At the third place, Mildred and Norman's (see photo above), we have been hanging drywall. We had to take down one ceiling -- ughh! -- and then put it back up. About two and a quarter rooms have been covered. Also, two large rooms have been taped and mudded.
Next week when our expanded crew arrives, there are several other homes that we will be working on. The NYS-FITS+ will really be hopping! Stay tuned.