Wednesday was Halloween and to observe the holiday we had a special meal, prepared by a very special chef -- our own, George Cheatle. Among other entrees on the menu we were offered: Old Blood Jello topped with Freshly Coagulated Blood and Cockroach Bodies in Moldy Cheese Sauce.

Our hungry builders devoured everything in site. There is something about tiling, grouting, painting window trim and installing new doors that builds the appetite!

Our efforts continue at a good pace.

Tuesday, October 30, 2007

Shop on Wheels

You might wonder what we use and how we get things done on site. Here's the answer, a photo of the back of JoEllen and Tom's pickup truck. Inside you can find one of almost anything: table saw, band saw, chop saw, drills, circular saw, air compressor, nailing guns and ammo, drywall tools, hammers, etc., etc. Each day on the job site we unload in the morning and reload in the evening. And, as you can see, they've learned how to back it quite neat and very full!

Tuesday began with unscheduled rain. It was annoying, because at one site most of our cutting is done outside. By 9 AM the skies began to clear, and soon we were going full speed again. It was a day of tiling, laying flooring, plumbing, more baseboard work, filling nail holes, adding a new door, and framing -- there's always another window to frame.

Monday, October 29, 2007

A Time to Rest, and Then...

The weekend brought a change of pace -- relaxation, exploration, extended time together. On Saturday some went on a Swamp Tour, hoping to catch sight of a few alligators. (And did.) They also walked a boardwalk through a colorful cypress swamp, replete with Spanish moss and bright yellow burr-marigolds flowers. Sunday's events included a Beignet run before worship at First Presbyterian, but not just a beignet-run; it was a comparison tasting Beignet run between two cafes. Food ended the day, too, -- a surprise birthday cake and ice cream to celebrate Debbie's special day.

Reinforcements were added to our number over the weekend. These included Rae Louise Tate (Star Lake), Marvin Spinner (ALbany), Linda and Peter Foss (Scarborough, ME). And arriving on Tuesday: Jack and Susan Abbott (Lake Luzerne).

On Monday we returned to work -- a prime coat on Yolanda's bedroom, continued tile and window trim work, some dry wall, baseboard, and finishing touches on AC and heating systems.

At Royden and Lina's a growing awareness of completion was in the air -- baseboard work continued, the last doors were hung and adjusted, the kitchen cabinets were leveled, tile sealing began, and windows prepared for painting. As the day was ending, the FEMA trailer was being prepared for removal. Completion will be a while, yet, but not long.

Sunday, October 28, 2007

They're the NYS-FITS+

He comes from New York or Penn State or Maine
She arrives by car, or by truck or by plane
They’re a student, a preacher, a clerk
They are here to do some hard work.
They’ve the NYS-FITS+


They wear their tool belts with pride
Their energy quite allied
They want the owners back at home
This is the reason they come
They’ve the NYS-FITS+

Each morning at dawn they arise
Rubbing the sleep from their eyes
After breakfast (by George) they will leave
Wearing their faith on their sleeve
They’ve the NYS-FITS+

They install doors, sheetrock and trim
And whether done by a her or a him
Each piece they install is with love
And confirmed by God up above
They’ve the NYS-FITS+

Those who came were not on their own
They got aid from the folk back at home
With their dollars and cares
And with all of their prayers
They’ve the NYS-FITS+

All too soon they will finish and go
And in each of their hearts they will know
That they gave it their best
They could do nothing less
They’ve the NYS-FITS+

by Tom Parsons, Lake Luzerne, New York

Thursday, October 25, 2007

A Good Day

We had a good day for construction -- sunny much of the time, temperate weather. The weather report had led us to believe we would have cloud cover and cooler weather. Delightfully wrong!

At Yolanda's house grout and trim work went forward. Our teachers included Ted Tate and Allen Mater. Marilyn was sanding and puttying. John worked on the AC most of the day. Ron Pedersen was responsible for cracking the whip! Most of the baseboard has been cut and ready for installation.

At Royden and Lina's Roland spent most of his day in the closet -- finishing the flooring. Kevin enlarged the size of the bathroom door from 24" to 30." JoEllen and Tom, envious of Roland, spent their day in another bathroom, alledgedly working on baseboard and quarter round. Deb was on her knees, pushing pink spackle into tiny little nail holes, then following up with a piece of sandpaper. Seth Honeyman was running the show, and Eric, though present, kept hiding from Seth's supervision -- when caught he helped Roland.

Wednesday, October 24, 2007

Hitting Stride

By Wednesday we have begun to hit our stride. Three home sites are being worked on, but our focus is really on just two of them. We hope to complete the rebuilding on at least one of the two.

At Royden and Lina's various floor and baseboard issues have been resolved, the threshold has been corrected, the sink has been centered, the cabinet installed above the stove, molding around the side door has been installed, the hallway and boy's bedroom flooring is almost complete. Seth seems well pleased with his crew!

At Yolanda's, interior window framing has continued, issues with the air conditioning system have been thought through, master bathroom has been sanded, drywall around the tub finished, taping and mudding underway, a door jam expanded to prepare for the baseboard molding, and the baseboard molding was continued. As you might have guessed, Ron is elated!

At the third place, Mildred and Norman's (see photo above), we have been hanging drywall. We had to take down one ceiling -- ughh! -- and then put it back up. About two and a quarter rooms have been covered. Also, two large rooms have been taped and mudded.

Next week when our expanded crew arrives, there are several other homes that we will be working on. The NYS-FITS+ will really be hopping! Stay tuned.

Tuesday, October 23, 2007

Treading Water in NOLA

Rain, rain and more rain. Because we have been getting so much rain (8" fell today - Monday - in some parts of NOLA -- schools and city offices closed early and Tulane University canceled classes), we began our work day by covering the floors of our houses with protective paper. However if you weren't soaked by the rain outside the house, the humidity got when you were working inside.

Ron and Seth are much closer to having clear lists of work to do, so that we can prioritize our tasks and make clear assignments. In some cases we are undoing work completed earlier, in others we are taking the next step, and in some we are still trying to figure out how to do what needs to be done. We'll begin to roll soon.

We continue to receive information about increasing financial support. Jeff White of Mediapolis, Iowa, has sent money to Bethany in Menands to support our work. Likewise, Sydney Lemire (age 6) had her dad, Jim, forward all the One Great Hour of Sharing money that she had saved this year -- $22.94! These last two push our total up to: $16,218. Never in our wildest dreams did we imagine we could raise this much!

Our last five rebuilders will be here tomorrow - Tuesday. Kevin and Allen have reached Birmingham, AL, and are within striking distance for Tuesday; JoEllen and Tom are still on the road and should be here tomorrow. Marcia should be here any minute - she was flying into TX.

Finally, you need to know that the weather forecast for tomorrow indicates that by mid-afternoon tomorrow - Tuesday - the rain should stop.